BC Hydro awards Site C turbine/generator contract

Despite lingering protests against it, the Site C project hit another milestone today.

BC Hydro has awarded German firm Voith the $470 million contract for the manufacturer and installation of six turbines and generators.

“The design and manufacture of these units is highly highly specialized work.” BC Hydro CEO Jessica McDonald said “There is only a limited number of companies internationally that are capable of supplying turbines and generators, they have to be custom designed for each hydroelectric facility.”

The supplier has a long history of supplying BC Hydro with turbines and generators dating back to 1930, for projects including: Revelstoke Unit 5 Project, Ruskin Dam and Powerhouse Upgrade, and the Gordon M. Shrum Turbine Replacement Project.

“Site C is currently the biggest energy infrastructure project in Canada. We are proud to bring new power generation capacity to this province.” Voith Canada CEO Bill Malus said

BC Hydro says the turbine-generator units are so large, the fuselage of a Boeing 747 could fit through the penstock. Each turbine-generator unit has an output of 250,000 horsepower, which is equivalent to about 600 Ford Mustang GTs at maximum power.

The turbine-generator section of the project will employ 150 workers at peak installation in 2022.

[youtube https://www.youtube.com/watch?v=RfN3rEg2YlA&w=560&h=315]

Something going on in the Cariboo you think people should know about?
Send us a news tip by emailing [email protected].

Continue Reading

ckbx Now playing play

cffm Now playing play

ckcq Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Williams Lake Fire Department To Hold Annual Food Drive

Members of the Williams Lake Fire Department are answering the call to help out the Salvation Army. Food Bank.

Regional Hospital Board Contribute Funding for Health Workers Childcare

The Cariboo Regional District is contributing funding to support the construction of a childcare centre with Interior Health. Finding a childcare and daycare centre in the Cariboo-Chilcotin is one of the main reasons bringing in long-term healthcare professionals to the region has been difficult, says Al Richmond, Chair of the Cariboo-Chilcotin Regional Hospital District Board (CCRHD).

Update: Severe Thunderstorm Watch and Warning over Quesnel

Environment Canada has issued a severe thunderstorm warning across the North Cariboo and in Quesnel.

G.R Baker Emergency Department Closed Until Morning

Northern Health advises Quesnel and area residents that the emergency room at G.R. Baker Memorial Hospital will be closed from 6:00 p.m. Friday, July 18, until 8:00 a.m. Saturday, July 19.

KIJHL Announce Home Openers For 2025/2026 Season

The KIJHL has announced the regular schedule and home openers for the 2025/2026 season. The regular season starts on September 19, and each team will compete in 44 games during the regular season, which concludes on February 28, 2026.
- Advertisement -