The contract to rebuild West Fraser Road in the Quesnel area has been awarded.

The Ministry of Transportation and Infrastructure will pay Enviro-Ex Contracting Ltd out of Prince George 37.7 million dollars to rebuild and realign the washed-out sections of the road.

Along with a new two-lane bridge over Narcosli Creek, 5.6 kilometres of paved two-lane road will be constructed on a new alignment on the east side of the creek.

“Since flooding washed out West Fraser Road back in spring 2018, we’ve been actively working on a long-term solution,” said Rob Flemming, Minister of Transportation and Infrastructure.   Construction is anticipated to begin next month on a new alignment that will restore direct access to Quesnel and provide a reliable route for people who live and work in the area.”

When completed, the new West Fraser Road will bypass the active slide areas along the washed-out portions and improve the safety and efficiency of the roadway.

The project is expected to be completed in the fall of 2023.

Esdilagh First Nation has an agreement with the ministry to clear the site in preparation for major road construction.

That work got underway in February.

The banks of Narcosli Creek will be protected with riprap to prevent further damage from the coming spring freshet, and that work is also underway through hired local equipment.

High water from the spring freshet in April of 2018 caused Narcosli Creek to erode five sections of West Fraser Road on the west side of the Fraser River, approximately 17 kilometres south of Quesnel.

The road was closed and residents out that way have been using a detour via the Garner and Webster Lake Roads ever since, which has added significant travel time.

Upon completion of the project, Emergency Management BC will submit a claim to the federal government for partial reimbursement through Disaster Financial Assistance Arrangements.

Something going on in the Cariboo you think people should know about?
Send us a news tip by emailing [email protected].

Continue Reading

ckbx Now playing play

cffm Now playing play

ckcq Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

‘Roos game to still go on despite afternoon fire at West Fraser Centre

A fire in the West Fraser Centre on Saturday afternoon almost caused the Quesnel Kangaroos' season opener against the Williams Lake Stampeders to be canceled. Crews were able to get on site and begin clean up in time, assuring that the game will go on.

Active wildfires update for the Cariboo Fire Centre

As of yesterday (Friday) there are currently 22 active wildfires within the Cariboo Fire Centre.

Infrastructure, housing, UNDRIP will top agenda as local governments meet in Victoria next week

Members of local governments and First Nations are gathering in Victoria next week for the annual Union of B.C. Municipalities (UBCM) convention.

B.C. Conservatives support federal bill to classify intimate partner killings as first-degree murder

B.C. politicians are voicing support for a federal Conservative bill that would classify the killing of an intimate partner as first-degree murder. 

Truck fire the cause of grassland fire near 100 Mile House ice rink

A truck caught fire on Wrangler Way in 100 Mile House, that spread onto the nearby grass, creating a wildland fire. 100 Mile House Fire Department was able to contain the blaze quickly, and report no one was injured.
- Advertisement -