The Johnston Bridge in Quesnel will now cost 15 million dollars for a repair and rebuild.
That is up from just over 8.8 million.
The price tag, revealed at Tuesday (Jan 6) night’s City Council meeting.
An inspection back in 2018 indicated some corrosion and Chris Coben, the Director of Capital Works & Infrastructure, told Council last night that things have gotten worse.
“A recent assessment confirmed that other than the pilings and the deck which are in good condition, the bridge is at its end of life. We confirm there is no longer an option to repair the bridge temporarily to keep it at a reduced weight limit from the original design as a long term solution. A rebuild is now the only solution to provide long term service for the city, so we’d be looking at a 30-plus, 30 to 50 year lifespan, with a full repair.”
There has been a 10,000 kilogram restriction on the bridge since 2018.
Coben says the main reason for the cost increase is inflation.
“There have been significant cost increases from 2018 to 2025, mainly due to increased inflation, additional structural deterioration occurring over the last number of years to keep the bridge remaining in service, and also enhanced inspections and the time overall it’s taken to have a construction ready project.”
Council asked Telus and Rogers to remove their infrastructure from the bridge back in May of 2021 and it wasn’t done until October of 2025.
Councillor Mitch Vik, also the Chair of the Finance Committee, asked how differently they could approach third party infrastructure, telecommunication companies for example, to motivate them in the future to do things more quickly.
Coben said it was a challenge for a number of reasons.
“That bridge is old. When that infrastructure was originally installed there was no formal agreement in place so that didn’t bode well for the city. The second piece, with them moving their infrastructure to an aerial crossing over the Quesnel River, was for their permitting aspect. Where an aerial crossing pertains you have to go through a different set of permits and processes as far as the Navigable Waters Act and getting approval for that. And of course they’re a private business so their contract that they have with their customers, they have service limitations. So those were all the challenges that we had to work through. It was slow, it was definitely challenging.”
The clock is ticking to get this project done as the city received a 6 million dollar grant from the Canada Community Building Fund back in 2023 that is approved until 2027, which means that the city must proceed with and complete the project prior to the end of 2027 or risk losing the approved grant funding.
The project was unanimously approved.
The city will have to dip into reserves for 5.2 million dollars and grants will cover the rest of the bill.
It’s expected to go out to tender next month and the expected completion date would be in December.
The bridge and the Riverfront Trail under the bridge would be fully closed to all traffic during the project.